SHANGHAI, Jul. 21 (SMM) – How Chinese NPI projects in Indonesia progress? Shanghai Metals Market gives you the latest update of major projects as of early July.
Company | Designed Capacity (1,000 mt, Ni content) | Output in 2015E (1,000 mt, Ni content) | Expected Commissioning | Possibility of Commissioning |
Tsingshan Group Phase 1 | 30 | 20 | Apr. 2015 | In operation |
Ningbo Brilli-Metal | 18 | 4.5 | Sept. 2015 | ★★★★★ |
Jiangpu Stainless Steel Manufacturing Co., Ltd. | 0.72 | 0.3 | Sept. 2015 | ★★★★★ |
Huadi Group | 1.2 | 0.5 | Sept. 2015 | ★★★★★ |
Ifishdeco | 0.4 | 0.03 | Nov. 2015 | ★★★★ |
Zhenshi Group | 5 | 2.5 | Dec. 2015 | ★★★★ |
Ningbo Brillimetal’s NPI project should be in a trial run July-August with monthly output estimated at 2,000 tonnes. The project is scheduled to start operation this September at its earliest.
Huadi Group completed equipment installation for its NPI project and will put it online in September at its earliest.
Zhenshi Group will delay commissioning of its NPI project to the end of this year due to technology problem, SMM learned. The Group imported 938.45 tonnes of ferronickel from Indonesia in April and May.
For news cooperation, please contact us by email: sallyzhang@smm.cn or service.en@smm.cn.
For queries, please contact William Gu at williamgu@smm.cn
For more information on how to access our research reports, please email service.en@smm.cn